1. TESTING
• Check the continuity signals and verify the polarity between transmitters and sensors with control room through junction box.
• safety relief valves ( using test bench up to 250 bar) according to the data sheets and process documents.
• Check the setting for control valves and check its feedback signals to control room.
• Check the instrumentation and control system for trace heating system.
• Inspect the control loop between site and DCS.
• Inspect the functional control for the local panels and/or main interlock panels.
• Simulation/Sourcing of 4 to 20 mA from Field devices to Control System and from Control System to Final Control Element(Control Valves, Shutdown Valves).
• Cause and Effects Checking
• Logic Testing from Control System.
• Testing of Alarms configured in the System against Instrument Parameters.
• Troubleshooting of Loops from Field to Control System.
• Testing and function testing of instruments on Human Machine Interface (HMI).
• Online Configuration through HART for SMART & Foundation Field bus Devices FF.
• Testing of Emergency Shutdown System (ESD) Loops
2. Commissioning
• Testing and commissioning of Turbine control systems MARK V ,MARK VI.
• Commissioning assistance to the clients for Oilfields, Gas Plants, Early Production Facilities (EPFs), Central Processing Facility (CPF).
• Prepare Loop Packages for all Field Instrumentation and submit to the client for checking and testing including the following forms;
• Insulation and Continuity Testing Report
• Calibration Report
• Loop Drawing for each Loop
• impulse Lines Pressure Testing Report.